Environmental Impact Assessment Agreement Governs the assessment of environmental impacts for development projects, specifying study parameters and reporting requirements.
1.1. Project Description and Objectives
The Consultant shall perform an Environmental Impact Assessment ("EIA") for the Green Valley Solar Farm Project (the "Project") to assess the potential environmental impacts pursuant to the United States laws and regulations, including but not limited to the National Environmental Policy Act ("NEPA").
1.2. Study Parameters
The Consultant shall conduct the EIA in accordance with the following study parameters:
2.1. Preparation of the EIA Report
The Consultant shall prepare a comprehensive EIA report ("EIA Report") detailing the methodology, findings, and recommendations of the study. The EIA Report shall include, at a minimum, the following sections:
2.2. Review and Approval of the EIA Report
Upon completion of the EIA Report, the Consultant shall submit the EIA Report to the Project Owner for review and approval. The Project Owner shall have thirty (30) days from the date of receipt of the EIA Report to review and provide written comments to the Consultant. The Consultant shall address Project Owner's comments and make necessary revisions to the EIA Report within ten (10) days of receiving Project Owner's comments. The Parties shall repeat this process until the EIA Report is deemed satisfactory by the Project Owner.
2.3. Regulatory Compliance and Government Filings
The Consultant shall submit the finalized EIA Report to the relevant authorities for the purpose of complying with the applicable United States laws and regulations. The Consultant shall make any necessary amendments to the EIA Report as required by the authorities and promptly resubmit the amended EIA Report for approval.
3.1. Development of an Environmental Management Plan
The Consultant shall develop and include an Environmental Management Plan ("EMP") in the EIA Report, which shall outline the proposed mitigation measures designed to minimize or eliminate the identified potential environmental impacts of the Project. The EMP shall, among other things, specify the responsibilities of the Project Owner and other parties regarding the implementation of mitigation measures, monitoring, and reporting requirements.
3.2. Monitoring and Evaluation
The Consultant shall, as part of the services under this Agreement, conduct regular monitoring and evaluation of the Project's environmental performance. The Consultant shall provide quarterly reports to the Project Owner on the effectiveness of the mitigation measures outlined in the EMP and recommend any necessary adjustments or additional measures.
4.1. Term of the Agreement
This Agreement shall commence on the Effective Date and shall continue in full force and effect until its termination by either Party as provided herein or until the completion of the services described herein to the satisfaction of the Project Owner, whichever occurs first.
4.2. Termination for Convenience
Either Party may terminate this Agreement at any time, with or without cause, upon thirty (30) days' prior written notice to the other Party.
4.3. Termination for Default
Either Party may terminate this Agreement upon written notice to the other Party if the other Party breaches a material term of this Agreement and fails to cure such breach within thirty (30) days following receipt of the written notice specifying the breach.
Consultant shall indemnify, defend, and hold harmless the Project Owner against any and all liability, loss, damages, claims, or causes of action, including reasonable attorney's fees and other legal costs, arising out of or in connection with the Consultant's performance of services under this Agreement, except to the extent caused by the gross negligence or willful misconduct of the Project Owner.
6.1. Governing Law
This Agreement shall be governed by and construed in accordance with the laws of the United States and the State of __________, without giving effect to any choice or conflict of legal principles or rules.
6.2. Dispute Resolution
Any dispute, controversy, or claim arising out of or relating to this Agreement or the breach thereof shall be first submitted to mediation. If the Parties are unable to resolve the dispute through mediation, the dispute shall be resolved by binding arbitration in accordance with the rules of the American Arbitration Association, and judgment upon the award rendered by the arbitrator(s) may be entered in any court having jurisdiction thereof.
7.1. Amendments
No amendment to or modification of this Agreement shall be effective unless it is in writing and signed by both Parties.
7.2. Assignment
Neither Party may assign this Agreement or delegate its duties or obligations under this Agreement without the prior written consent of the other Party, which consent shall not be unreasonably withheld or delayed.
7.3. Entire Agreement
This Agreement constitutes the entire agreement between the Parties concerning the subject matter hereof and supersedes all prior agreements and understandings, whether written or oral, relating to the subject matter. This Agreement may not be amended except in writing signed by both Parties.